Scenario lens
Stress-test the pathway
Controls alter likelihood—not impact. They are sensitivity tests, not forecasts.
Executive decision support · Analysis baseline: 24 September 2026
A whole-of-tournament risk view across facilities, finance, institutions, operations, people and legacy—designed to test what must be true for East Africa to deliver well.
Scores are working judgments from public reporting and Brian Wesaala’s analysis. Every risk is labelled by evidence status.
Scenario lens
Controls alter likelihood—not impact. They are sensitivity tests, not forecasts.
Decision signal
High
Executive priority
The critical distinction
Venues, training sites, overlays and formal testing.
Governance, people, security, systems, mobility and legacy.
5 × 5 qualitative matrix
Geographic lens
Scores compare the risks in this register, not country performance or CAF compliance status.
Action agenda
Living risk register
Filter, rank, and open any risk to inspect indicators, mitigation, ownership and evidence status.
| Risk | Geography | Category | Evidence | Likelihood | Impact | Exposure | Owner |
|---|
Transparent by design
The desk uses a qualitative likelihood × impact model aligned to common project-risk practice. It makes assumptions visible, distinguishes source strength, and keeps facility compliance separate from end-to-end tournament readiness.
Likelihood and impact are each rated 1–5. Exposure is their product. 20–25 is Critical, 12–19 High, 6–11 Moderate, and 1–5 Low.
Risks are grouped using familiar project domains: scope, schedule, cost, quality, resources, procurement, governance, communications, legal, security, technology, team services, operations and benefits.
Verified means supported by an attributable primary or high-reliability source. Reported means credible public reporting. Assumption means a proposition to validate.
Controls adjust likelihood according to each risk’s sensitivity. Impact remains fixed. Results show direction and concentration—not statistical probability.
Assumption ledger
Selected public basis
This is not a comprehensive evidence repository. Risk owners should replace working assumptions with dated source records, inspection outputs, milestones and accountable actions.
Football as Infrastructure
Submit dated, attributable information about AFCON 2027 investment or delivery. Every submission enters a private review queue. It will not alter the assessment or appear publicly unless it is independently assessed and verified.